Rebranded trains are running on the Cairngorm funicular under test conditions
At a glance
Trains are running on the Cairngorm funicular for the first time since late 2018, but under test conditions
The UK's highest railway was closed to the public four years ago because of structural problems
Owner Highlands and Islands Enterprise said work to reinstate the railway was in its final stages
It hopes to have it operational again early next year – but at a cost of £25m
Trains are running again on the Cairngorms mountain railway for the first time in four years – though under test conditions for now.
The UK's highest railway has been closed to visitors since September 2018 due to structural problems.
Highlands and Islands Enterprise (HIE), which owns the funicular and the snowsports centre it serves, said work to reinstate the railway had reached the final stages.
The Scottish government agency said trains could be fully operational early next year.
But it added that project costs had risen from about £16m to £25m due to the impacts of Covid, Brexit and blizzards in spring hampering repairs.
The funicular has been closed to the public since September 2018
The Scottish government had provided a £16m funding package towards the costs.
HIE said it had reallocated uncommitted funds from its wider Cairngorm snowsports centre masterplan capital investment package to meet the additional costs.
The agency added that the Scottish government also allocated £7m additional funding in June 2022.
Opened in 2001 at a cost of £26m, the funicular connects a base station with a restaurant and a ski area 1,097m (3,599ft) up Cairn Gorm mountain near Aviemore.
Repairs to the railway started in April 2021.
Testing on the funicular is expected to continue into December and safety certificates will be needed from the UK Department for Transport before it can be opened to visitors.
There has been criticism of the efforts to get the railway operational again.
Last year, mountaineer and author Cameron McNeish, who opposed the plans for the funicular before it was opened in 2001, said the railway should be "stripped" from the mountainside and the area allowed to go back to the wild.
UK's highest railway could open next year
Delays hit reopening of mountain railway
Mountain railway demolition cost 'more than £13m'
CairnGorm: Where did the money go?
Weather warning: All the disruption caused by heavy rain on Thursday
Highland health fears over climate emergency
Dobbies Inverness hosts charity Christmas Shopping Night
Spirits high as Fort William gear up for Ross-shire road trip
3 budget talking points as Chancellor urged to deal with cost of living crisis, freeports and windfall tax
Music for MS gig in Thurso raises £3610 for charity
Republicans win House control with narrow majority
Xi criticises Trudeau in awkward exchange at G20
Ukraine not to blame for Poland missile – Zelensky
The X-rated cartoon that shocked the US
The sand battery making waves in Finland
The mindset employers want now
© 2022 BBC. The BBC is not responsible for the content of external sites. Read about our approach to external linking.